In the Select phase of investment management, on which three criteria are projects analysed and ranked before a portfolio is chosen?
Show the answer
Answer: C. Benefit, cost and risk
SP 800-100's Select phase screens new proposals, then scores and ranks every project on what it returns, what it costs and what it risks, before a portfolio is fixed and review points are set.
Source: NIST SP 800-100 (NIST) — Sec. 5.1 Legislative Overview