In the Select phase of investment management, on which three criteria are projects analysed and ranked before a portfolio is chosen?

  1. Complexity, duration and the vendor proposed to deliver it
  2. Urgency, executive sponsor and headcount required
  3. Benefit, cost and risk
  4. Compliance, audit findings and precedent
Show the answer

Answer: C. Benefit, cost and risk

SP 800-100's Select phase screens new proposals, then scores and ranks every project on what it returns, what it costs and what it risks, before a portfolio is fixed and review points are set.

Source: NIST SP 800-100 (NIST) — Sec. 5.1 Legislative Overview