A manager must explain what risk framing produces. What is its principal output under SP 800-39?
Show the answer
Answer: C. The risk management strategy, addressing how the organisation will assess, respond to and monitor risk
SP 800-39 states risk framing establishes context and a common perspective on managing risk, and produces as its principal output a risk management strategy addressing how the organisation intends to assess, respond to and monitor risk.
Source: NIST SP 800-39 (NIST) — Sec. 3.1 Framing Risk