A residual risk accepted two years ago is still recorded as acceptable, and nobody has revisited it. Why does SP 800-39 regard that as a problem?
Show the answer
Answer: B. Acceptability depends on the tolerance threshold and residual risk moves over time, so the judgement must be revisited
SP 800-39 makes acceptability a comparison against the tolerance threshold, and residual risk does not stand still. A judgement made two years ago says nothing about today's position.
Source: NIST SP 800-39 (NIST) — Ch. 1 footnote on residual risk