A security manager is asked which outcomes a governance programme should deliver for risk management under SP 800-39. Which two are among the five named outcomes? Choose two.
Show the answer
Answer: B. Strategic alignment of risk decisions with the mission
A. Performance-based outcomes through measuring and reporting risk metrics
SP 800-39 lists five governance outcomes: strategic alignment, execution of the risk process, efficient resource allocation, performance-based outcomes through metrics, and delivered value. Eliminating residual risk is not achievable and is not an outcome.
Source: NIST SP 800-39 (NIST) — Sec. 2.3.1 Governance