A supplier is onboarded and the first security review takes place six months into the contract. Which CSF 2.0 outcome does this arrangement miss?
Show the answer
Answer: B. Planning and due diligence are performed to reduce risks before entering formal supplier relationships
CSF 2.0 subcategory GV.SC-06 places planning and due diligence before entry into a formal supplier relationship, so that risk is reduced at selection rather than managed after the contract is signed.