Which pairing correctly distinguishes residual risk from target residual risk in IR 8286?
Show the answer
Answer: A. Residual risk is what remains after the response is applied; target residual risk is the desired state derived from appetite and tolerance
IR 8286 records residual risk as the post-response assessment, and target residual risk as a desired risk state that the organisation may document based on its risk appetite and tolerance.
Source: NIST IR 8286 (NIST) — Sec. 3 Risk Register Elements