Controls have been deployed to treat a risk, and the register records the treatment as complete. Which follow-up does IR 8286 say is usually missing?
Show the answer
Answer: A. Analysis after deployment to determine whether risk actually fell within the established tolerance
IR 8286 observes that once controls go in, hardly anyone goes back to check whether risk actually came down inside the tolerance that was set. Deployment gets recorded as if it were the outcome.
Source: NIST IR 8286 (NIST) — Sec. 2.2.2 Informal Analysis Methods