CISM study material · question 280 of 1000
After treatment, actual residual risk is measured higher than the target residual risk that was set. What does this indicate under IR 8286?
Show the answer
Answer: C. The response has not achieved what was intended, since actual residual risk should be equal to or less than target
IR 8286 sets the expectation that risk left after management acts should sit at or below the target. Coming in above it means the response did not do what it was meant to do.
Source: NIST IR 8286 (NIST) — Sec. 3.2 Identify the Risks