Which two symptoms does IR 8286 attribute to overconfidence in risk work? Choose two.
Show the answer
Answer: A. Unreasonably low likelihood estimates for threat events
C. An exaggerated estimation of the organisation's ability to handle a threat
IR 8286's overconfidence shows up as optimism about scenarios: likelihoods pitched too low, opportunity benefits talked up, and the organisation's own capacity to cope with a threat overrated.
Source: NIST IR 8286 (NIST) — Sec. 3.2.2 Determination of Potential Threats