The window in which a particular risk could have occurred has now passed and its risk reserve is unspent. What does IR 8286 say should happen, and what does it require?
Show the answer
Answer: D. The reserve can be released for other predetermined funding needs, which requires prior coordination with budget owners
IR 8286 allows an unspent reserve to be freed for other funding needs already identified once the risk has passed or been reduced, provided owners have coordinated with acquisition and budget holders beforehand.
Source: NIST IR 8286 (NIST) — Sec. 3.5.3 When a Risk Event Passes