Which two activities belong to the preparation step of a risk assessment under SP 800-30? Choose two.
Show the answer
Answer: B. Identifying the assumptions and constraints under which the assessment is conducted
D. Identifying the sources of threat, vulnerability and impact information to be used
SP 800-30's preparation step identifies the purpose, the scope, the assumptions and constraints, the information sources, and the risk model and analytic approach. Likelihood determination belongs to the conduct step.
Source: NIST SP 800-30 Rev. 1 (NIST) — Sec. 3.1 Preparing for the Risk Assessment