An assessment team decides for itself how wide the assessment will be. Who does SP 800-30 say determines the scope?
Show the answer
Answer: B. The organisational official requesting the assessment, together with the risk management strategy
SP 800-30 states risk assessment scope affects the range of information available for risk-based decisions and is determined by the organisational official requesting the assessment and the risk management strategy.
Source: NIST SP 800-30 Rev. 1 (NIST) — Task 1-2 Identify Scope