SP 800-39 distinguishes a course of action from a risk response measure. Which pairing is correct?
Show the answer
Answer: A. A course of action combines and phases several response measures; a response measure is one specific act against an identified risk
SP 800-39 defines a course of action as a time-phased or situation-dependent combination of risk response measures, and a risk response measure as a specific action taken to respond to an identified risk.
Source: NIST SP 800-39 (NIST) — Sec. 3.3 Responding to Risk