Which four things does a plan of action and milestones do for security weaknesses found in programmes and systems?

  1. Identifies, assesses, prioritises and monitors the progress of corrective efforts
  2. Detects, contains, eradicates and recovers
  3. Frames, assesses, responds and monitors
  4. Categorises, selects, implements, assesses and authorises each of the affected systems in turn
Show the answer

Answer: A. Identifies, assesses, prioritises and monitors the progress of corrective efforts

SP 800-100 gives the plan of action and milestones four jobs against weaknesses in programmes and systems: find them, judge them, rank them, and track the fixes through to completion.

Source: NIST SP 800-100 (NIST) — Table 2-1 Plans of Action and Milestones