A programme manager reports the percentage of systems that have been authorised. Which type of metric is this?

  1. An implementation metric
  2. A mission impact metric
  3. An effectiveness metric
  4. An efficiency metric
Show the answer

Answer: A. An implementation metric

NIST gives the percentage of systems accredited as a commonly used implementation metric, answering whether the manager is implementing the tasks for which they are responsible.

Source: NIST SP 800-100 (NIST) — Sec. 7.1 Metric Types