A programme manager reports the percentage of systems that have been authorised. Which type of metric is this?
Show the answer
Answer: A. An implementation metric
NIST gives the percentage of systems accredited as a commonly used implementation metric, answering whether the manager is implementing the tasks for which they are responsible.
Source: NIST SP 800-100 (NIST) — Sec. 7.1 Metric Types