- Home
- All questions
- Question 463
CISM study material · question 463 of 1000
An organisation's monitoring strategy is drafted at the business process tier. What does SP 800-137 require before it takes effect?
Show the answer
Answer: B. Officials at the organisation tier review and approve it, so risk tolerance across all missions is properly considered
SP 800-137 sends a strategy drafted at Tier 2 up to Tier 1 for review and approval, so that tolerance across every mission and business process has been weighed before it takes effect.
Source: NIST SP 800-137 (NIST) — Sec. 3.1.1 Organization and Mission Tier Strategy