A supplier suffers a disruption but does not report it, arguing it was not serious. Which contract provision does NIST say should have prevented the dispute?
Show the answer
Answer: B. Baseline criteria in the contract determining whether a disruption qualifies as serious
SP 800-161r1 states contracts should set processes and protocols for communicating and reporting vulnerabilities, incidents and other business disruptions, including acceptable deviations and baseline criteria to determine whether a disruption qualifies as serious.
Source: NIST SP 800-161 Rev. 1 (NIST) — Sec. 3.1.2 The Role of C-SCRM in the Acquisition Process