Requirements are flowed down to subcontractors but nothing checks whether they are met. Which linkage does NIST require?
Show the answer
Answer: B. Performance objectives tied to a method of inspection, such as a quality assurance surveillance plan
SP 800-161r1 pairs flowed-down requirements with supply chain performance objectives and a named inspection method — a quality assurance surveillance plan or its equivalent — so performance is actually monitored.
Source: NIST SP 800-161 Rev. 1 (NIST) — Sec. 3.1.2 The Role of C-SCRM in the Acquisition Process