A learning programme manager struggles to justify the programme to executives. Which linkage does NIST say demonstrates why it is needed?

  1. Documenting how the learning strategy supports the goals of the organisation's risk management strategy
  2. Listing the certifications held by the training team
  3. Benchmarking the programme's cost against peer organisations
  4. Reporting the number of courses delivered last year
Show the answer

Answer: A. Documenting how the learning strategy supports the goals of the organisation's risk management strategy

SP 800-50r1 states that documenting the learning programme strategy and how it supports the goals of the organisation's risk management strategy shows executive leadership why the programme is needed.

Source: NIST SP 800-50 Rev. 1 (NIST) — Sec. 2.1 Building the Strategic Plan