What does NIST say a cost-benefit analysis for security product selection should include, beyond the alternatives under consideration?
Show the answer
Answer: A. A life cycle cost estimate for the status quo as well as for each identified alternative
SP 800-100 wants the do-nothing option priced too: a life cycle cost estimate for staying as things are, one for each alternative, and the benefits each alternative brings out.
Source: NIST SP 800-100 (NIST) — Ch. 12 Security Services and Products Acquisition