Why does NIST require changes to be tested before implementation?
Show the answer
Answer: D. So the effects of the change can be observed, minimising the risk of adverse results in production
SP 800-100 requires changes to be tested first so their effects are seen before production feels them, which is what keeps adverse results down.
Source: NIST SP 800-100 (NIST) — Ch. 14 Configuration Management