Which two things does the baseline configuration control require an organisation to maintain? Choose two.
Show the answer
Answer: C. A current baseline configuration of the system
D. An inventory of the system's constituent components
The baseline configuration control has the organisation develop, document and keep current both a baseline configuration for the system and an inventory of the components making it up.