Why does NIST say the configuration management process can only begin after the initial control baseline is selected?
Show the answer
Answer: C. There must be a baseline before there can be a controlled deviation from it
SP 800-100 states that during acquisition and development, initial baselines of security controls are selected based on the assessed risk level, and after the security controls are established the configuration management process can begin.
Source: NIST SP 800-100 (NIST) — Sec. 14.1 CM in the System Development Life Cycle