Which three decisions can conclude a change request under NIST's process?
Show the answer
Answer: C. Approve, deny, or defer pending further testing or analysis
SP 800-100 states that once a change has been evaluated and tested, one of three actions is taken: approve, with implementation authorised; deny, an immediate refusal; or defer, postponing the decision pending further testing or analysis.
Source: NIST SP 800-100 (NIST) — Sec. 14.3 Step 3 Implementation Decision