Which two considerations govern the scheduling of a planned disconnection, according to NIST? Choose two.

  1. Completing the disconnection before the next audit cycle
  2. Aligning the disconnection with the end of the financial year
  3. Allowing reasonable time for both sides to make internal business arrangements
  4. Conducting the disconnection when the impact on users is minimal
Show the answer

Answer: C. Allowing reasonable time for both sides to make internal business arrangements
D. Conducting the disconnection when the impact on users is minimal

SP 800-100 asks for enough lead time that both sides can plan internally, and for the cut itself to fall when it will disturb users least.

Source: NIST SP 800-100 (NIST) — Sec. 6.3 Terminating Interconnection