Which two things does NIST require after an emergency disconnection? Choose two.

  1. Automatic termination of the underlying agreements
  2. Immediate verbal notification of the other party, with confirmation of receipt
  3. A joint press statement issued by both organisations
  4. Written notification in a timely manner explaining the incident and when the link might be restored
Show the answer

Answer: B. Immediate verbal notification of the other party, with confirmation of receipt
D. Written notification in a timely manner explaining the incident and when the link might be restored

SP 800-100 has the owner or designee tell the other side verbally at once and confirm they heard, then follow with timely written notice covering what happened, why and how the link was cut, and what restoration would need.

Source: NIST SP 800-100 (NIST) — Sec. 6.3.1 Emergency Disconnection