An organisation trained on the earlier NIST incident response guidance is updating to Revision 3. What structural change must it explain to staff?
Show the answer
Answer: A. The four-phase cycle was replaced by a model built on the six CSF 2.0 functions, so preparation is no longer a phase of its own
SP 800-61r3 replaces the previous four-phase life cycle with a model based on the six CSF 2.0 functions, in which Govern, Identify and Protect are preparation activities outside incident response itself.
Source: NIST SP 800-61 Rev. 3 (NIST) — Sec. 2.1 Incident Response Life Cycle Model