Which two plans might executing the incident response plan require the organisation to activate as well? Choose two.
Show the answer
Answer: A. The business continuity plan
B. The disaster recovery plan
SP 800-61r3 recommends initiating execution of other cybersecurity plans as needed, such as business continuity and disaster recovery plans, to support incident response.
Source: NIST SP 800-61 Rev. 3 (NIST) — Table 3 RS.MA-01.R3