Which sequence does NIST describe when a disaster forces relocation of several systems?
Show the answer
Answer: C. The disaster recovery plan transfers operations to the alternate site, then each system's contingency plan restores, recovers and tests that system
SP 800-34r1 has the disaster recovery plan move the site first; each affected system then falls back on its own contingency plan to restore, recover, test and return to service.