Which sequence does NIST describe when a disaster forces relocation of several systems?

  1. The continuity of operations plan supersedes both
  2. Both plans are executed simultaneously by separate teams
  3. The disaster recovery plan transfers operations to the alternate site, then each system's contingency plan restores, recovers and tests that system
  4. Each system's own contingency plan runs first to restore that system, and the disaster recovery plan then consolidates all of them at the alternate site afterwards
Show the answer

Answer: C. The disaster recovery plan transfers operations to the alternate site, then each system's contingency plan restores, recovers and tests that system

SP 800-34r1 has the disaster recovery plan move the site first; each affected system then falls back on its own contingency plan to restore, recover, test and return to service.

Source: NIST SP 800-34 Rev. 1 (NIST) — Sec. 2.2.7 Information System Contingency Plan