During a continuity of operations activation, what does the business continuity plan cover in NIST's model?
Show the answer
Answer: D. The functions that are not mission essential, sustained alongside the essential ones
SP 800-34r1's plan table describes the business continuity plan as process-focused and states it may be used with a continuity of operations plan to sustain non-mission-essential functions.
Source: NIST SP 800-34 Rev. 1 (NIST) — Table 2-2 Type of Plans