Why is recovery point objective not counted as part of maximum tolerable downtime, while recovery time objective is?
Show the answer
Answer: A. Because it concerns lost data rather than elapsed outage
SP 800-34r1 states that unlike recovery time objective, recovery point objective is not considered part of maximum tolerable downtime — its concern is lost data, not the duration of the outage.
Source: NIST SP 800-34 Rev. 1 (NIST) — Sec. 3.2.1 Determine Business Processes and Recovery Criticality