The achievable recovery time objective exceeds a maximum tolerable downtime that cannot be relaxed. What does NIST direct?
Show the answer
Answer: D. Record the gap in a plan of action and milestones and plan its mitigation
SP 800-34r1 directs that where the recovery time objective cannot be met and the maximum tolerable downtime is inflexible, a plan of action and milestones should document the situation and plan for mitigation.
Source: NIST SP 800-34 Rev. 1 (NIST) — Sec. 3.2.1 Determine Business Processes and Recovery Criticality