Which two elements does NIST expect a contingency test to exercise? Choose two.
Show the answer
Answer: C. Restoring the system onto substitute hardware from backups
B. Connectivity inside and outside the organisation and performance on the substitute hardware
SP 800-34r1 wants a test to prove the substitute kit really works: the system brought back onto it from backups, links reaching both inside and outside the organisation, and the throughput it manages once it is running there.
Source: NIST SP 800-34 Rev. 1 (NIST) — Sec. 3.5.1 Testing