Which two elements does NIST expect a contingency test to exercise? Choose two.

  1. The insurer's claims process
  2. Connectivity inside and outside the organisation and performance on the substitute hardware
  3. Restoring the system onto substitute hardware from backups
  4. The organisation's public communications procedures
Show the answer

Answer: C. Restoring the system onto substitute hardware from backups
B. Connectivity inside and outside the organisation and performance on the substitute hardware

SP 800-34r1 wants a test to prove the substitute kit really works: the system brought back onto it from backups, links reaching both inside and outside the organisation, and the throughput it manages once it is running there.

Source: NIST SP 800-34 Rev. 1 (NIST) — Sec. 3.5.1 Testing