To which organisational process does NIST tie contingency plan maintenance?
Show the answer
Answer: A. The change management process, so plan review is triggered by system change
SP 800-34r1 states contingency plans should be reviewed and updated as part of the organisation's change management process, tying plan maintenance to system change rather than leaving it standalone.
Source: NIST SP 800-34 Rev. 1 (NIST) — Sec. 3.6 Plan Maintenance