Which criterion does NIST include among the bases for activating a contingency plan?
Show the answer
Answer: D. Whether the outage is expected to run longer than the recovery time objective
SP 800-34r1 states activation criteria may be based on the extent of any damage to the system, the criticality of the system to the mission, and the expected duration of the outage lasting longer than the recovery time objective.
Source: NIST SP 800-34 Rev. 1 (NIST) — Sec. 4.2.1 Activation Criteria and Procedure