Which range must notification procedures cover, per NIST?
Show the answer
Answer: A. Both outages that come with warning, such as a forecast hurricane, and those that come with none, such as equipment failure
SP 800-34r1 states notification procedures should be documented for both types of disruption — those with prior warning, such as a hurricane forecast, and those with no warning, such as equipment failure or a criminal act.
Source: NIST SP 800-34 Rev. 1 (NIST) — Sec. 4.2.2 Notification Procedures