Study. uk . com
  1. Home
  2. All questions
  3. Question 972

CISM study material · question 972 of 1000

Which further work can fall inside the reconstitution phase when the original facility is unrecoverable?

  1. Reactivating the continuity of operations plan
  2. Extending the alternate site occupancy indefinitely
  3. Preparing an entirely new permanent location
  4. Re-running the business impact analysis
Show the answer

Answer: C. Preparing an entirely new permanent location

SP 800-34r1 states reconstitution may also include preparing an entirely new permanent location to support system processing requirements, where the original facility cannot be recovered.

Source: NIST SP 800-34 Rev. 1 (NIST) — Sec. 4.4 Reconstitution Phase