CISM study material · question 99 of 1000
A system is about to go live and the project manager proposes assessing control effectiveness after six months of operation. Why does SP 800-39 place that assessment earlier?
Show the answer
Answer: A. The implementation phase is the opportunity to determine control effectiveness before operations commence
SP 800-39 states the implementation phase provides the opportunity to determine the effectiveness of selected controls before actual operations commence, so expectations can be compared against real behaviour.
Source: NIST SP 800-39 (NIST) — Sec. 2.5 Tier Three — Information Systems View