Which two scoping options does NIST allow for a business continuity plan? Choose two.
Show the answer
Answer: B. Covering the processes of a single business unit
C. Covering only the functions deemed to be priorities
SP 800-34r1 lets the plan cover one business unit's processes or the whole organisation's, and allows a narrower cut confined to the functions treated as priorities.
Source: NIST SP 800-34 Rev. 1 (NIST) — Sec. 2.2.1 Business Continuity Plan