Why must the business continuity planner coordinate with system owners?
Show the answer
Answer: C. So that what the continuity plan promises matches what the supporting systems can actually deliver
SP 800-34r1 states that because business processes use information systems, the continuity planner must coordinate with system owners to ensure the plan's expectations and the systems' capabilities are matched.
Source: NIST SP 800-34 Rev. 1 (NIST) — Sec. 2.2.1 Business Continuity Plan