Why must the business continuity planner coordinate with system owners?

  1. So that the continuity plan can be approved by the authorising official for each one of the affected systems
  2. So that each one of the system owners is able to approve the order in which the recovery work actually happens
  3. So that what the continuity plan promises matches what the supporting systems can actually deliver
  4. So that the cost of the whole plan can be allocated across each one of the individual system budgets that are held at present
Show the answer

Answer: C. So that what the continuity plan promises matches what the supporting systems can actually deliver

SP 800-34r1 states that because business processes use information systems, the continuity planner must coordinate with system owners to ensure the plan's expectations and the systems' capabilities are matched.

Source: NIST SP 800-34 Rev. 1 (NIST) — Sec. 2.2.1 Business Continuity Plan