CISM study material · question 866 of 1000

Which sequence matches NIST's seven-step contingency planning process?

  1. Business impact analysis, contingency planning policy, contingency strategies, preventive controls, plan development, plan maintenance, and then testing
  2. Business impact analysis, preventive controls, contingency planning policy, testing, contingency strategies, plan development, and then plan maintenance
  3. Policy, strategies, business impact analysis, plan development, preventive controls, testing, maintenance
  4. Policy, business impact analysis, preventive controls, contingency strategies, plan development, testing/training/exercises, plan maintenance
Show the answer

Answer: D. Policy, business impact analysis, preventive controls, contingency strategies, plan development, testing/training/exercises, plan maintenance

SP 800-34r1 sets out seven steps: develop the contingency planning policy, conduct the business impact analysis, identify preventive controls, create contingency strategies, develop the contingency plan, ensure plan testing, training and exercises, and ensure plan maintenance.

Source: NIST SP 800-34 Rev. 1 (NIST) — Ch. 3 Contingency Planning Process