Where in the system life cycle does NIST place the contingency planning policy and the business impact analysis, and why there?
Show the answer
Answer: D. Early, before the system is categorised, so that recovery needs shape the design
SP 800-34r1 places contingency planning policy and the business impact analysis early in the system development life cycle, before system categorisation, so the recovery requirements they produce influence the system's design.
Source: NIST SP 800-34 Rev. 1 (NIST) — Ch. 3 Contingency Planning Process