Which four inputs does NIST say determine system resource recovery priorities, and where does that step sit?
Show the answer
Answer: C. Process criticality, outage impacts, tolerable downtime and system resources — the last step of the business impact analysis
SP 800-34r1 makes identifying system resource recovery priorities the final business impact analysis step, developed from process criticality, outage impacts, tolerable downtimes and the system resources involved.
Source: NIST SP 800-34 Rev. 1 (NIST) — Sec. 3.2.3 Identify System Resource Recovery Priorities