On NIST's alternate-site comparison, which row matches a warm site?

  1. Full provision, short setup time
  2. Full provision with real-time mirroring already in place, and no setup time at all
  3. Partial hardware and telecommunications provision, medium setup time
  4. No hardware or telecommunications provided at all, and a long setup time on arrival
Show the answer

Answer: C. Partial hardware and telecommunications provision, medium setup time

SP 800-34r1's sample alternate site criteria table shows the cold site with none for equipment and telecommunications and long setup time, the warm site partial with medium setup time, and the hot site full with short setup time.

Source: NIST SP 800-34 Rev. 1 (NIST) — Table 3-34 Sample Alternate Site Criteria