A plan relies on a mobile site delivered within a day. Which caveat does NIST attach?

  1. The mobile site cannot support any system that has been categorised as either moderate or high impact
  2. The delivery window applies only to those sites that are within the same region as the estate itself
  3. Mobile sites require a reciprocal agreement to be in place
  4. Installing and setting up its equipment lengthens the actual response time beyond delivery
Show the answer

Answer: D. Installing and setting up its equipment lengthens the actual response time beyond delivery

SP 800-34r1 notes mobile sites can often be delivered within 24 hours, but that the time to install and set up the equipment increases the actual response time.

Source: NIST SP 800-34 Rev. 1 (NIST) — Sec. 3.4.3 Alternate Sites