Which contractual detail does NIST say determines whether an alternate site's capacity will actually be available?

  1. The site's own certification against a recognised international security standard
  2. The number of other clients subscribed to the same site and resources
  3. The vendor's guaranteed response time after a disaster has been formally declared
  4. The length of the contract term that has been agreed with the alternate site vendor itself
Show the answer

Answer: B. The number of other clients subscribed to the same site and resources

SP 800-34r1 states the alternate site agreement should record the number of organisations allowed to use the site concurrently and the number subscribed to the same resources, which determines whether capacity is really there.

Source: NIST SP 800-34 Rev. 1 (NIST) — Sec. 3.4.3 Alternate Sites