Which review does NIST require before an alternate site agreement is relied on?
Show the answer
Answer: A. Review and approval by the legal department of each party
SP 800-34r1 states the legal department of each party must review and approve the alternate site agreement before it is relied upon.
Source: NIST SP 800-34 Rev. 1 (NIST) — Sec. 3.4.3 Alternate Sites