When a catastrophe affects many of a vendor's clients at once, which organisations commonly receive the highest replacement priority?
Show the answer
Answer: A. Those whose processes people's health and safety depend on
SP 800-34r1 notes that in a catastrophic disaster involving many of a vendor's clients, the organisations with health- and safety-dependent processes will most likely receive the highest priority for replacement shipments.
Source: NIST SP 800-34 Rev. 1 (NIST) — Sec. 3.4.4 Equipment Replacement