When a catastrophe affects many of a vendor's clients at once, which organisations commonly receive the highest replacement priority?

  1. Those whose processes people's health and safety depend on
  2. Those with the shortest recovery time objectives
  3. Those with the largest contract value
  4. Those that declared the disaster first
Show the answer

Answer: A. Those whose processes people's health and safety depend on

SP 800-34r1 notes that in a catastrophic disaster involving many of a vendor's clients, the organisations with health- and safety-dependent processes will most likely receive the highest priority for replacement shipments.

Source: NIST SP 800-34 Rev. 1 (NIST) — Sec. 3.4.4 Equipment Replacement