CISM study material · question 958 of 1000
Which priority does NIST place above the speed of outage assessment?
Show the answer
Answer: B. Personnel safety
SP 800-34r1 states outage assessment should be completed as quickly as conditions permit, with personnel safety being the highest priority throughout.
Source: NIST SP 800-34 Rev. 1 (NIST) — Sec. 4.2.3 Outage Assessment