Which element belongs in an outage assessment under NIST guidance?

  1. The potential for further damage as well as the cause of the outage
  2. The deadline by which the applicable regulator has to be notified of the outage
  3. The cost that the outage has caused the organisation to date in lost trading revenue
  4. The residual risk that will remain once all of the recovery work has been completed
Show the answer

Answer: A. The potential for further damage as well as the cause of the outage

SP 800-34r1 lists outage assessment elements including the cause of the outage, the potential for additional disruption or damage, the status of physical infrastructure, the functional status of equipment, the type of damage, items to be replaced, and the estimated time to restore service.

Source: NIST SP 800-34 Rev. 1 (NIST) — Sec. 4.2.3 Outage Assessment